22 sept

D 1st slab
E parking columns
Water tank work
G footings

Thursday, September 10, 2009

D and e building

Plinth ready and getting ready for 1st slab

Monday, August 3, 2009

Weekly update

D/e building nearing plinth

Saturday, August 1, 2009

Sunday, July 26, 2009

26th july 2009

D/E building footings complete